Ground Floor Slab Casting
Ground floor slab casting at Zenith Residences is now complete, marking a key milestone as the project progresses steadily into vertical construction.
Latest construction updates and progress for Zenith Residences.
-1.png&w=2048&q=75)
Ground floor slab casting at Zenith Residences is now complete, marking a key milestone as the project progresses steadily into vertical construction.
Core wall casting is now underway, marking the vertical progression of the structure as the building begins to rise. In parallel, tower crane installation has been successfully completed, enabling efficient execution of upcoming structural works and accelerating overall site productivity. With critical infrastructure now in place, construction continues to advance on schedule, with further progress updates to follow.
All structural and pre-raft inspections have been successfully completed and formally approved. With reinforcement, formwork, and waterproofing inspections cleared, the project is fully prepared for raft casting. Raft casting has since commenced as of February 20 — a dedicated video update on that milestone will follow.
Steel reinforcement works completion marks a key structural milestone in the foundation phase of ZENITH. This stage ensures load distribution, structural integrity, and readiness for subsequent concrete works.
During the rain period the Zenith site had little to no rain and water proofing had already been completed.
.jpg&w=2048&q=75)
Construction at Zenith Residences is progressing remarkably ahead of schedule, with piling and slab work complete. The engineering team has successfully completed critical groundwork milestones.