Zenith Residences

Latest construction updates and progress for Zenith Residences.

2nd Floor Slab Casting – Pour 1
08.18.2026
Construction Update

2nd Floor Slab Casting – Pour 1

The first slab casting pour for the 2nd floor is underway at Zenith Residences, marking the next stage of structural development as the project continues its vertical rise.

Learn more
1st Floor Slab Casting – Pour 2
07.31.2026
Construction Update

1st Floor Slab Casting – Pour 2

The second slab casting pour for the 1st floor is progressing at Zenith Residences, continuing the project’s structural advancement as construction moves further into the upper levels.

Learn more
Slab casting pour 1 1st floor
07.27.2026
Construction Update

Slab casting pour 1 1st floor

The first slab casting pour for the 1st floor is underway at Zenith Residences, marking another key stage in the project’s structural development as construction continues its vertical progress.

Learn more
2nd to 3rd Podium Ramp Casting
07.11.2026
Construction Update

2nd to 3rd Podium Ramp Casting

Ramp casting from Podium 2 to Podium 3 is progressing at Zenith Residences, marking another step forward in the completion and connectivity of the project’s podium structure.

Learn more
Vertical Casting from Podium 3 to 1st Floor
07.04.2026
Construction Update

Vertical Casting from Podium 3 to 1st Floor

Vertical casting works from Podium 3 to the 1st floor are progressing at Zenith Residences, marking the next stage in the project’s structural development as the building continues its vertical rise.

Learn more
 Podium 3 Completion
06.26.2026
Construction Update

 Podium 3 Completion

Podium 3 completion at Zenith Residences marks another significant construction milestone, as the project continues progressing ahead of schedule and advancing steadily through its podium and superstructure development phase.

Learn more
Ramp Casting
06.13.2026
Construction Update

Ramp Casting

Ramp casting at Zenith Residences marks another important construction milestone, as the project continues progressing ahead of schedule and advancing steadily through its podium and superstructure development phase.

Learn more
Vertical Casting P2 to P3
06.03.2026
Construction Update

Vertical Casting P2 to P3

Vertical casting from Podium 2 to Podium 3 at Zenith Residences marks another important construction milestone, as the project continues progressing ahead of schedule and advancing steadily through its superstructure development phase.

Learn more
Podium 2 Slab Casting
05.23.2026
Construction Update

Podium 2 Slab Casting

Podium 2 slab casting at Zenith Residences marks another significant construction milestone, as the project continues progressing ahead of schedule and advancing steadily through its superstructure development phase.

Learn more
Podium 1 Slab Casting
05.08.2026
Construction Update

Podium 1 Slab Casting

Podium 1 slab completion at Zenith Residences marks another major construction milestone as the project continues advancing steadily through its vertical development phase.

Learn more
Ground Floor Slab Casting
03.23.2026
Construction Update

Ground Floor Slab Casting

Ground floor slab casting at Zenith Residences is now complete, marking a key milestone as the project progresses steadily into vertical construction.

Learn more
Core Wall Casting & Tower Crane Installation
03.07.2026
Construction Update

Core Wall Casting & Tower Crane Installation

Core wall casting is now underway, marking the vertical progression of the structure as the building begins to rise. In parallel, tower crane installation has been successfully completed, enabling efficient execution of upcoming structural works and accelerating overall site productivity. With critical infrastructure now in place, construction continues to advance on schedule, with further progress updates to follow.

Learn more
Structural Inspections Approved
02.16.2026
Construction Update

Structural Inspections Approved

All structural and pre-raft inspections have been successfully completed and formally approved. With reinforcement, formwork, and waterproofing inspections cleared, the project is fully prepared for raft casting. Raft casting has since commenced as of February 20 — a dedicated video update on that milestone will follow.

Learn more
Steel Reinforcement Completion
01.12.2026
Construction Update

Steel Reinforcement Completion

Steel reinforcement works completion marks a key structural milestone in the foundation phase of ZENITH. This stage ensures load distribution, structural integrity, and readiness for subsequent concrete works.

Learn more
Water Proofing Complete
12.12.2025
Construction Update

Water Proofing Complete

During the rain period the Zenith site had little to no rain and water proofing had already been completed.

Learn more
Piling
09.23.2025
Construction Update

Piling

Construction at Zenith Residences is progressing remarkably ahead of schedule, with piling and slab work complete. The engineering team has successfully completed critical groundwork milestones.

Learn more